Union Renovation/Expansion
Goals of the Renovation/Expansion
• Create a student union that is user-friendly, brighter,
comfortable ("homey"), and student- oriented.
• Expand the facilities available to the campus community
for programming and meetings.
• Create a Student Involvement Center that brings together
student organizations into one location and ties them more closely
to the Student Activities office.
• Renovate Dining Services facilities to create a facility
that provides more flexibility to meet the changing needs of students
and a more comfortable dining experience for students.
• Create a front door for the campus.
• Bring student services to the students through an Integrated
Services Concept which includes admissions, financial aid, cashier,
registrar, orientation and Ranger Card.
• Firmly establish the student union as the center of student
life and activities on campus.
• Correct infrastructure problems and upgrade aging building
structures.
Building History
• The Parkside Union was built in 1976 at a cost of $3.5
million, funded entirely by Student Fees.
• The Parkside Union was redecorated and refurbished in
the spring of 1989.
• In 2004, the Segregated Fee Allocation Committee and Parkside
Student Government Association approved $21 million in student
fees to fund a renovation and expansion of the current facility.
• In 2006, the Segregated Fee Allocation committee approved
an additional 1.1 million for the project.
Need for Renovation
The University of Wisconsin - Parkside Student Union facility,
constructed in 1976, provides minimal space for Student Activities
and Student Life programming needs. Due to budgetary constraints,
the small amount of programming space planned for the Student
Union was eliminated during original construction. The campus
was entirely a commuter institution until 1986 when the first
residence hall (University Apartments) was constructed. With the
addition of a second residence hall (Ranger Hall) in 1997, the
campus established an on campus residence hall population of over
800 students. Future plans include constructing additional residence
hall space. The demands for student activities and student life
programming space has increased dramatically since Ranger Hall’s
opening. Considering the strain on existing space the current
residence halls have created, future residence halls cannot be
pursued until an adequate Union facility is developed.
The relocation of the Bookstore and student organizations from
Wyllie Hall to the Student Union allows Information Services,
Library Services, and other Student Services needs to be met within
Wyllie Hall; the relocation of the Office of Admissions and student
organizations from Molinaro Hall to the Student Union allows the
School of Business & Technology, Geography, Geology, and Sociology/Anthropology
needs to be met within Molinaro Hall; and the relocation of auxiliary
vendors and student organizations from Greenquist Hall to the
Student Union allows the Biology, Chemistry, Mathematics, and
Nursing program needs to be met within Greenquist Hall.
Student
Union Financial Facts
Estimated Costs
Construction:
$18,362,000
Hazardous Materials Abatement: $100,000
A/E Design & Other Fees: $1,651,000
DSF Project Management: $798,000
Contingency: $1,477,000
Movable Equipment: $923,000
Special Equipment: $1,200,000
Percent for Art: $61,000
Estimated Total Project Cost: $24,572,000
*Note: The architects will verify these costs during the early
phases of design. Costs are subject to change due to fluctuations
in construction materials and stainless steel.
Renovation/Expansion financing
The Parkside Union Renovation/Expansion is estimated
to cost $24.57 million.
The funding sources for are: $23 million in Student Fees and $1.5
million in General Program Revenue dollars.
There may be revisions to the budget during the renovation, due
to the competitive construction market, changes to the scope of
the project, and unanticipated expenses for Food Service and AV/Technical
Equipment.
Budget Revisions
Any budget revisions will be reported in this section
over the course of the project.
Student Fees
The student fees to support the project are spread out
over 30 years. In the 2004-05 school year the student fee to support
the Parkside Union Renovation/Expansion is $95.52 per student.
This will increase to approximately $400.00 per student over the
next three years. For the remainder of the life of the bond the
per student fee will be dependent on enrollment.