| Segregated
Fee Allocation Decision |
X |
Feb.
2004 |
| Program
Statement Finalized |
X |
Dec.
2004 |
| Student
Gov. Recommends Names for Leadership Team |
X |
Dec.
2004 |
| Sent
Request for Proposal(RFP) for Architectural Services |
X |
Feb.
2005 |
| RFP Proposals
Reviewed |
X |
Mar.
2005 |
| Architectural
Services Selection |
X |
Apr.
2005 |
| Visioning
Exercise held with Architects |
X |
Jun.
2005 |
| 10% Design
Approval |
X |
Oct.
2005 |
| Design
Report 35% Preliminary Plans Submitted |
X |
Mar.
2006 |
| Board
of Regents Approval |
X |
Apr.
2006 |
| State
Building Commission Authority to Construct |
X |
Apr.
2006 |
| Bid Opening |
X |
Nov.
2006 |
| Start
Construction |
|
Feb.
2007 |
| Ground
Breaking |
|
Mar.
2007 |
| Substantial
Completion |
|
Mar.
2009 |
| Reopening
Celebration |
|
Sept.
2009 |